Marietta's 2023 citywide asphalt resurfacing project will begin Sept. 11.
The milling and paving work is being done by Shelly and Sands and will follow the schedule below, weather permitting.
Milling:
Sept. 11
¯ Virginia Street (Gilman Avenue to corporation limit)
¯ Harmar Street (Virginia Street to Market Street)
¯ Ohio Street (Front Street to Post Street)
¯ Alley east of Third Street (Putnam Street to Butler Street)
¯ Indian Acres parking lot
Sept. 12
¯ Lafayette/Olney (Lafayette Place to Pike Street)
¯ Alley north of Greene Street (Vine Street to Colegate Drive)
¯ Oakwood Street (Colegate Drive to Terrace Avenue)
Sept. 18
¯ Greene Street (Hardwood Center Drive to Acme Street).
Paving:
Sept. 12
¯ Alley east of Third Street (Putnam Street to Butler Street) base layer.
¯ Indian Acres parking lot, base layer.
Sept. 13
¯ Indian Acres parking lot, surface layer
¯ Ohio Street (Front Street to Post Street) surface layer
¯ Harmar Street (Virginia Street to Market Street) surface layer.
Sept. 14
¯ Alley east of Third Street (Putnam Street to Butler Street) surface layer
¯ Virginia Street (Gilman Avenue to corporation limit) surface layer.
Sept. 15
¯ Lafayette/Olney (Lafayette Place to Pike Street) base layer
¯ Oakwood Street (Colegate Drive to Terrace Avenue) surface layer.
Sept. 16:
¯ Lafayette/Olney (Lafayette Place to Pike Street) surface layer
¯ Alley north of Greene Street (Vine Street to Colegate Drive) surface layer.
Sept. 18
¯ Greene Street (Hardwood Center Drive to Acme Street) base layer
Sept. 19
¯ Greene Street (Hardwood Center Drive to Acme Street) intermediate layer.
Sept. 26:
¯ Greene Street (Hardwood Center Drive to Acme Street) surface layer.
Adjustments of utilities (manholes and water valves) are scheduled for the week of Sept. 18-22. Pavement markings will follow.Parking will be prohibited in some locations during resurfacing activities. Residents should note No Parking signs and dates and times of work.
Traffic will be maintained with occasional exceptions while positioning and staging equipment. Motorists traveling those areas should use caution and obey traffic control signs and flagging personnel.
Any questions should be directed to the City of Marietta Engineering Department, 740-373-5495.